Construction Labour Measurement in Reinforced Concrete Floating Caissons in Maritime Ports

Identificadores
URI: http://hdl.handle.net/20.500.12251/3068
Ver/Abrir: https://www.scopus.com/inward/record.uri?eid=2-s2.0-85127777039&doi=10.28991%2fCEJ-2022-08-02-01&partnerID=40&md5=fcb17fe0934a717a13cb2f4229e979fa
ISSN: 2676-6957
DOI: 10.28991/CEJ-2022-08-02-01
Compartir
Estadísticas
Ver Estadísticas de uso
Metadatos
Mostrar el registro completo del ítem
Autor
Pérez Díaz, Pedro Antonio; Martín Dorta, Norena Natalia; Gutiérrez García, Francisco Javier
Fecha
2022
Materia/s

Estructura flotante

Gestión de proyectos

Gestión de la producción

Estructuras - Construcción

Materia/s Unesco

3305.15 Ingeniería Hidráulica

3305.11 Puertos

3305.32 Ingeniería de Estructuras

5311.04 Organización de Recursos Humanos

5311.02 Gestión Financiera

Resumen

This research work attempts to approach the measuring of the working equipment necessary to make floating caissons for maritime work and their performances. With this objective, an empirical study has been carried out based on the construction of five floating caissons with a rectangular layout of 34.00 meters in length, 17.00 meters in width, and 19.00 meters in depth, lightened with 32 vertical cells. This work was carried out in the port of Granadilla, Tenerife (Spain). The updated scientific literature related to the execution of this type of floating structure refers to the importance of the calculation hypotheses, the actions to be taken into account, the service states or the importance of the choice of materials (concrete and steel). However, scientific research does not seem to face the problem of how to size the working team necessary to execute this type of structure. The work force is approached from the point of view of the adequate sizing of working groups. The important contribution of the article to the project and construction management literature is the development and capability of an easy-to-use optimization model for planning the labour and labour days required in floating caisson construction. The optimization model proposed in this research allows the project managers of a construction company to estimate the labour costs and teams necessary in the execution of the construction. This gives it a competitive advantage both in the construction phase and in the bidding phase for the award of the work. © 2022 by the authors. Licensee C.E.J, Tehran, Iran.

This research work attempts to approach the measuring of the working equipment necessary to make floating caissons for maritime work and their performances. With this objective, an empirical study has been carried out based on the construction of five floating caissons with a rectangular layout of 34.00 meters in length, 17.00 meters in width, and 19.00 meters in depth, lightened with 32 vertical cells. This work was carried out in the port of Granadilla, Tenerife (Spain). The updated scientific literature related to the execution of this type of floating structure refers to the importance of the calculation hypotheses, the actions to be taken into account, the service states or the importance of the choice of materials (concrete and steel). However, scientific research does not seem to face the problem of how to size the working team necessary to execute this type of structure. The work force is approached from the point of view of the adequate sizing of working groups. The important contribution of the article to the project and construction management literature is the development and capability of an easy-to-use optimization model for planning the labour and labour days required in floating caisson construction. The optimization model proposed in this research allows the project managers of a construction company to estimate the labour costs and teams necessary in the execution of the construction. This gives it a competitive advantage both in the construction phase and in the bidding phase for the award of the work. © 2022 by the authors. Licensee C.E.J, Tehran, Iran.

Colecciones
  • Artículos en revistas científicas

Listar

Todo RIARTEComunidades y ColeccionesAutoresTítulosMateriasMaterias UnescoTipos de documentosEsta colecciónAutoresTítulosMateriasMaterias UnescoTipos de documentos

Mi cuenta

AccederRegistro

Estadísticas

Ver Estadísticas de uso

Ayuda

Sobre RIARTEPreguntas frecuentesLocalizar informaciónPolíticasPolítica de Protección de Datos

Políticas Editoriales OA

Logo SHERPA/RoMEOLogo Dulcinea

Difusión de contenido

Logo RecolectaLogo Hispana

Copyright © Consejo General de la Arquitectura Técnica 2018 | Aviso Legal | Política de Protección de Datos

Facebook
Twitter
Contacto Sugerencias